Earned Value Method Management Applied to The Construction of The Multifamily Building – Lima, Peru 2020

Authors

  • FRANZ HERNANDEZ
  • DORIS ESENARRO
  • CIRO RODRIGUEZ
  • LORENA VELA
  • ROBERT CALVO

Keywords:

Management, earned value, schedule, control.

Abstract

This research aims to assess costs and time in the study of the earned value method management applied to the construction of the multifamily building in Lima, it is worth mentioning that the main problem of low productivity rates is the low cost control, that affects directly the performance of projects. The methodology used in this context is the earned value, which allows managing the costs and time of projects, gaining as a result the S curve and the control table, as a conclusion it could be said that the companies should maintein a correct control of time and cost of projects, because as it can be seen, at the end of the project, the company will have a lost of money for S/ 134,176.33 soles from month 06, which represents the 1.94% at the end of the Project.

Downloads

Download data is not yet available.

References

Sanchez, C. (2019). Gestión del valor ganado para mejorar el control de costos y tiempo en obras civiles en la refinería la pampilla (período 2016-2017). Lima, Peru. [Master’s Thesis, Federico Villarreal National University]. Recovered from: http://repositorio.unfv.edu.pe/bitstream/handle/UNFV/3416/UNFV_Sanchez_Caceres_Caceres_Carlos_Enr ique_Maestria_2019.pdf?sequence=1&isAllowed=y

Losano, S., Patiño, I., Gomes, A., Torres, A.(2018), “Identificación de factores que generan diferencias de tiempo y costos en proyectos de construcción en Colombia”, ing.cienc. Vol.14 No.27, pp.1. Recovered from: http://www.scielo.org.co/scielo.php?script=sci_arttext&pid=S1794-91652018000100117&lang=es

Albayrak, G., Özdemir, I (2018). Multimodal optimization for time-cost trade-off in construction projects using a novel hybrid method based on FA and PSO. Construction Magazine Vol.17 No.2, pp.1. Recovered from: https://scielo.conicyt.cl/scielo.php?script=sci_arttext&pid=S0718-915X2018000200304&lang=es

Emar, M., Akcay,C., Manisali, E. Time-cost optimization using harmony search algorithm in construction projects. Construction Magazine Vol.18 No.2, pp.1. Recovered from: https://scielo.conicyt.cl/scielo.php?script=sci_arttext&pid=S0718-915X2019000200226&lang=es

Santelices, C., Herrera, R., Muñoz,F. Problems in quality management and technical inspection of work: a study applied to the chilean context. Rev. ing. constr.Vol.34 No.3, pp. 1-2. Recovered from: https://scielo.conicyt.cl/scielo.php?script=sci_arttext&pid=S0718-50732019000300242&lang=es

Gabriele, G., Navarro, D. (2015). Control de obra del proyecto multifamiliar “los fresnos” a través de la gestión del valor ganado (evm). Lima, Peru. [Undergraduate thesis, Ricardo Palma University]. Recovered from: http://repositorio.urp.edu.pe/bitstream/handle/URP/2239/gabriele_gc- navarro_dhn.pdf?sequence=1&isAllowed=y

Chavez, J. (2018). Implementación de la metodología del valor ganado para controlar los costos de una obra conexa en la minera cerro corona, 2017. Lima, Peru. [Undergraduate thesis, Trujillo National University]. Recovered from:

http://dspace.unitru.edu.pe/bitstream/handle/UNITRU/11034/CHAVEZ%20RUIZ%20JONATAN%20ROG ELIO.pdf?sequence=1&isAllowed=y

Delgado, D (2014). Método de Valor Ganado como herramienta Lean Construction. Valencia, España. [End of degree project, Polythecnic University of Valencia]. Recovered from: https://riunet.upv.es/bitstream/handle/10251/48335/Trabajo%20Final%20Grado.pdf?sequence=1&isAllowe d=y

Durand, J (2018). Propuesta de gestión del planeamiento de obras de edificación mediante la metodología de líneas de flujo, el valor ganado y el resultado operativo proyectado en pequeñas y medianas empresas. Lima, Peru. [Undergraduate thesis, Pontifical Catholic University of Peru]. Recovered from: http://tesis.pucp.edu.pe/repositorio/handle/20.500.12404/12510

Fuente, R. (2016). Método de valor ganado (EMV): Aplicado en la gestión de proyectos de edificación en España. Madrid, España. [Doctoral thesis, European University]. Recovered from: file:///C:/Users/Franz/Downloads/Tesis%20Ra%C3%BAl%20Fuente%20Jurid%C3%ADas%20(1).pdf

Gutierrez, V y Serrano, E (2015). Sistematización del control de costos en pequeñas empresas de construcción civil. Peru. Lima, Peru. [Undergraduate thesis, Peruvian University of Applied Sciences]. Recovered from:

https://repositorioacademico.upc.edu.pe/bitstream/handle/10757/592806/SERRANO_SE.pdf?sequence=1& isAllowed=y

Mendoza, W. (2019). Implementación del last planner y la metodología del valor ganado en proyectos civiles “Construccion de puentes”, red vial 5- huacho. Huancayo, Perú. [Undergraduate thesis, Nacional University of Central Perú]. Recuperado de: http://repositorio.uncp.edu.pe/bitstream/handle/UNCP/5555/T010_44573636_T.pdf?sequence=1&isAllowe d=y

Herrera, R., Muñoz, F., Avila, B (2020), “Key requirements of an IT tool based on last planner® system”, Rev. ing. constr. Vol.35 No.2, pp.1. Recovered from: http://dx.doi.org/10.4067/S0718-50732020000200126

Diaz, L., De olivera, M., Pucharelli, P., Pinzón, J. (2019), “Integration between the Last Planner System and the Quality Management System Applied in the Civil Construction Industry”, Rev. ing. constr. Vol.34 No.2, pp.1. Recovered from: http://dx.doi.org/10.4067/S0718-50732019000200146

Andrade, M., Arrieta, B. (2011), “Last planner system results in subcontract construction company”, Construction Magazine. Vol.10 No.1, pp.36-52. Recovered from: http://dx.doi.org/10.4067/S0718- 915X2011000100005

Google Maps (2020), “Peru map”. Recovered from: https://www.google.com/maps/place/Per%C3%BA/@- 6.1493494,- 70.5176523,4356332m/data=!3m1!1e3!4m5!3m4!1s0x9105c850c05914f5:0xf29e011279210648!8m2!3d- 10.4391955!4d-75.3881836

Downloads

Published

2021-06-30

How to Cite

HERNANDEZ, F. ., ESENARRO, D. ., RODRIGUEZ, C. ., VELA, L. ., & CALVO, R. . (2021). Earned Value Method Management Applied to The Construction of The Multifamily Building – Lima, Peru 2020. The Journal of Contemporary Issues in Business and Government, 27(3), 838–848. Retrieved from https://cibgp.com/au/index.php/1323-6903/article/view/1675

Most read articles by the same author(s)